| No. |
Location |
|
Description of works |
|
Project Image |
| |
Year 2005 |
|
|
|
|
| 1 |
Repair Work to Pump Room (Deck 1 & 2) at Jurong Shipyard |
|
Concrete Repair |
|
|
| 2 |
TGU 11.7m-13.2m high f/f north wall external pre-packed aggregate
grout repair at Shell Bukom |
|
Prepacked Grouting |
|
|
| 3 |
Coring work |
|
Coring work |
|
|
| 4 |
Repair to defective concrete structure at CD5 Pumpstreet Structure
at Shell Bukom |
|
Concrete Repair |
|
|
| 5 |
Repair concrete structure at CD5 Exchanger Area at Shell Bukom |
|
Concrete Repair |
|
|
| 6 |
Investigate/repair spalled concrete prestressed beam Wharf 10 at Shell
Bukom |
|
Concrete Repair |
|
|
| 7 |
Repair to spalling concrete for building at Senoko Power Station |
|
Prepacked Grouting & Patch Repair |
|
|
| 8 |
Bridge 3 , Pipe rack and HF Jetty Maintenance Protective coatings
to steel piles at Shell Bukom |
|
Protective coatings to steel piles |
|
|
| 9 |
Bridge 3 , Pipe rack and HF Jetty Maintenance Epoxy Crack repair and
protective coatings to concrete underdeck at Shell Bukom |
|
Epoxy Crack Repair, Protective coatings to concrete underdeck |
|
|
| 10 |
Bridge 3 , Pipe rack and HF Jetty Maintenance Prepacked Grouting Repair
and Cementitious Crack Repair at Shell Bukom |
|
Prepacked Grouting and cementitious crack repair |
|
|
| 11 |
TGU RAM Severe 12m High South Wall External at Shell Bukom |
|
Prepacked Grouting |
|
|
| 12 |
TGU RAM High 8.6m Beams GL A4-B23 at Shell Bukom |
|
Prepacked Grouting |
|
|
| 13 |
TGU RAM High 5.5m Beams GL A4-B23 at Shell Bukom |
|
Prepacked Grouting |
|
|
| 14 |
TGU RAM Severe 5.5m High Beams A5/B5, A7/B7, f/f A10/A11/A12, E7017-4
slab repair at Shell Bukom |
|
Prepacked Grouting |
|
|
| 15 |
Repair to defective concrete structure (RAM H6) at CD5 Complex at
Shell Bukom |
|
Prepacked Grouting |
|
|
| 16 |
Repair to damaged concrete structure at CD3/LND Piperack at Shell
Bukom |
|
Prepacked Grouting to Pipe Rack Pillars |
|
|
| 17 |
Reconstruction of Slab between E1306/E1309 at Shell Bukom |
|
Hacking of existing slab and recasting |
|
|
| 18 |
Repair to cracked edges at circular slab openings for C2501, V2501,
C2506 & C3507 at CD 3 Complex at Shell Bukom |
|
Prepacked Grouting to Slabs edges |
|
|
| 19 |
Proposed erection of 3-sty place of worship with 1 basement carpark
as an extension to the existing 2-sty church at 5 Tavistock Ave |
|
Post Tensioning Work |
|
|
| 20 |
Repair to Defective/spalling concrete surface at column and slab at
HVU (LOC) Complex at Shell Bukom |
|
Prepacked Grouting to columns and slabs |
|
|
| 21 |
Repair to defective RC stumps at Battery limit gridline 1-5/P-R at
Shell Bukom |
|
Prepacked Grouting to column stumps |
|
|
| 22 |
Repair to Defective/Spalling Concrete surface at CD5 complex, Shell
Bukom |
|
Prepacked Grouting to columns and beams |
|
|
| 23 |
Repair to Defective/Spalling Concrete surface for column & beam
at PL-3 complex at Shell Bukom |
|
Prepacked Grouting to columns and beams, including temporary props
using Steel I-Beam |
|
|
| 24 |
Repair to Defective/Spalling Concrete surface for column & beam
at PL-3 complex at Shell Bukom |
|
Prepacked Grouting to columns and beams, including temporary props
using Steel I-Beam |
|
|
| 25 |
Temporary Propping Works for Repair to Pillars at TGU Complex (S7
Category) at Shell Bukom |
|
Temporary Propping Works for Repair to existing 9 columns using SHS
props |
|
|